Court: the power outage justified the delay in signing the state contract

30 November 2021, Tuesday

The winner did not sign the contract on time and did not ensure its execution. The controllers included the information in the RNP.
The courts did not support them, because the winner: did
not sign the contract and did not ensure its execution on time due to the lack of electricity on the last day for this. The technical problem is confirmed by the letter of the HOA;
he fulfilled his obligations the next day and informed the customer that he did not want to evade the contract;
conscientiously worked with the customer on similar transactions;
provided services under a previously concluded contract and after inclusion in the RNP.
Note that in practice there is another opinion. Thus, the AC of the Ural District supported the decision to include information about the winner in the RNP: a power outage is not a reason not to sign a contract on time. The winner could make a deal elsewhere and not on the last day for this.
Document:Resolution of the AC of the North Caucasus District of 18.11.2021 in case N A 63-1177/2021