The customer held a construction auction with additional requirements. To confirm the experience, the participant submitted, among other things, a copy of the subcontracting agreement. He was allowed to purchase.
The supervisors decided that in this case only contracts or general contracts are suitable. However, the courts supported the customer: it does not matter whether the participant was a general contractor or a subcontractor.
Note: FAS has repeatedly expressed otherwise.
Document:
Resolution of the AS of the West Siberian District of 14.10.2021 in case N A03-14737/2020