If during the execution of the construction contract circumstances arise due to which it cannot be executed, then in 2022, among other things, you can change:
- volume and (or) types of work under the contract, specifications and types of equipment from the project documentation;
- the amount of the advance. On this basis, it can also be established if the parties have not done this before;
- the procedure for acceptance and payment of a separate stage of the execution of the contract, the results of the work performed.
Changes can be made within the LBO.
To do this, the counterparty sends the customer a documented proposal and a signed draft agreement on the adjustment of the contract.
The customer has 10 business days to:
- sign the agreement, send it to the counterparty and include information about the changes in the register of contracts;
- inform the counterparty in writing about the refusal to sign and justify it.
The government recommends that customers also take into account innovations under Law N 223-FZ.
The changes took effect April 18.
Document: Decree of the Government of the Russian Federation of April 16, 2022 N 680