The winner did not sign the contract on time. The customer recognized him as evading.
The supervisors did not include the information in the RNP, because the winner
did not fulfill his obligations in a timely manner due to the fact that the authorized employee (director) fell ill. In the sick list there are dates of disability that fell during the period of signing the contract;
issued the contract security;
informed the customer about the reason for the delay.
A similar position is taken, in particular, by the Ulyanovsk UFAS.
Note that in practice there is another opinion.
Document:The decision of the FAS of Russia dated 03.12.2021 in the case N 21/44/104/573 GAS